Case law Brussels I Regulation
(44/2001)
Article 6 of the Brussels I Regulation
(Art. 6 BR I = Art. 6 BC 1968)
Two or more defendants [Article 6, point (1)]
ECJ
22 May 2008 ‘Glaxosmithkline v Rouard’ (Case C-462/06, ECR
2008 Page I-03965)
The rule of special jurisdiction provided for in
Article 6, point (1), of the Brussels I Regulation cannot be applied
to a dispute falling under Section 5 of Chapter II of that Regulation
concerning the jurisdiction rules applicable to individual contracts
of employment.
It is apparent from Article 18(1) of that Regulation
and, moreover, from a literal interpretation of Section 5, supported
by the ‘travaux préparatoires’ relating to the
Regulation, that the court having jurisdiction in proceedings concerning
an individual contract of employment must be designated in accordance
with the jurisdiction rules laid down in that Section, rules which,
on account of their specific and exhaustive nature, cannot be amended
or supplemented by other rules of jurisdiction laid down in that regulation
unless specific reference is made thereto in Section 5.
As regards the possibility that only an employee
may rely on Article 6, point (1), of the Brussels I Regulation, that
would run counter to the wording of both that provision and Section
5 of Chapter II of that Regulation. The transformation by the Community
courts of the rules of special jurisdiction, aimed at facilitating
sound administration of justice, into rules of unilateral jurisdiction
protecting the party deemed to be weaker would go beyond the balance
of interests which the Community legislature has established in the
law as it currently stands. Furthermore, such an interpretation would
be difficult to reconcile with the principle of legal certainty, which
is one of the objectives of the regulation and which requires, in
particular, that rules of jurisdiction be interpreted in such a way
as to be highly predictable (see paras 19-24, 32-33, 35, operative
part).
ECJ
11 October 2007 ‘Freeport v Arnoldsson’ (Case
C-98/06, ECR 2007 p. I-08319)
Article 6, point (1), of the Brussels I Regulation
is to be interpreted as meaning that the fact that claims brought
against a number of defendants have different legal bases does not
preclude application of that provision.
Although the wording of that provision does not
show that the conditions laid down for its application include a requirement
that the actions brought against different defendants should have
identical legal bases, it must however be ascertained whether, between
various claims brought by the same plaintiff against different defendants,
there is a connection of such a kind that it is expedient to determine
those actions together in order to avoid the risk of irreconcilable
judgments resulting from separate proceedings. For decisions to be
regarded as contradictory, it is not sufficient for there to be a
divergence in the outcome of the dispute.
In addition, that provision applies where
claims brought against different defendants are connected when the
proceedings are instituted, to avoid the risk of irreconcilable judgments
resulting from separate proceedings, without there being any further
need to establish separately that the claims were not brought with
the sole object of ousting the jurisdiction of the courts of the Member
State where one of the defendants is domiciled (see paras 38-40, 47,
52, 54, operative part 1-2)
ECJ
13 July 2006 ‘Reisch Montage v Kiesel’ (Case
C-103/05, ECR 2006 p. I-06827)
Article 6, point (1), of the Brussels I Regulation
must be interpreted as meaning that that provision may be relied on
in the context of an action brought in a Member State against a defendant
domiciled in that State and a co-defendant domiciled in another Member
State even when that action is regarded under a national provision
as inadmissible from the time it is brought in relation to the first
defendant, such as a rule precluding creditors from bringing individual
actions against a debtor who has been declared bankrupt. First, that
provision does not include any express reference to the application
of domestic rules or any requirement that an action brought against
a number of defendants should be admissible, by the time it is brought,
in relation to each of those defendants under national law. Second,
since it is not one of the provisions which provide expressly for
the application of domestic rules and thus serve as a legal basis
therefor, that provision cannot be interpreted in such a way as to
make its application dependent on the effects of domestic rules. However,
that same provision cannot be interpreted in such a way as to allow
a plaintiff to make a claim against a number of defendants for the
sole purpose of removing one of them from the jurisdiction of the
courts of the Member State in which that defendant is domiciled (see
paras 27, 30-33, operative part).
ECJ
13 July 2006 ‘Roche v Primus and Goldenberg’ (Case
C-539/03, ECR 2006 p. I-06535)
Article 6, point 1, of the 1968 Brussels Convention
[Article 6, point 1, of the Brussels I Regulation] must be interpreted
as meaning that it does not apply in European patent infringement
proceedings involving a number of companies established in various
Contracting States [Member States] in respect of acts committed in
one or more of those States even where those companies, which belong
to the same group, may have acted in an identical or similar manner
in accordance with a common policy elaborated by one of them. Since
neither the patent infringements of which the various defendants are
accused nor the national law in relation to which those acts are assessed
are the same, there is no risk of irreconcilable decisions being given
in European patent infringement proceedings brought in different Contracting
States, since possible divergences between decisions given by the
courts concerned would not arise in the context of the same factual
and legal situation. It follows that the connection required for Article
6, point 1, of the Brussels Convention [Article 6, point 1, of the
Brussels I Regulation] to apply cannot be established between such
actions (see paras 20, 25, 27-28, 31, 33, 35, 41, operative part).
ECJ
27 October 1998 ‘Réunion v Spliethoff's (Case
C-51/97, ECR 1998 p. I-06511)
Article 6, point 1, of the 1968 Brussels Convention
[Article 6, point 1, of the Brussels I Regulation] must be interpreted
as meaning that a defendant domiciled in a Contracting State [Member
State] cannot, on the basis of that provision, be sued in another
Contracting State [Member State] before a court seised of an action
against a co-defendant not domiciled in a Contracting State [Member
State] on the ground that the dispute is indivisible rather than merely
displaying a connection. The objective of legal certainty pursued
by the Convention [Regulation] would not be attained if the fact that
a court in a Contracting State [Member State] had accepted jurisdiction
as regards one of the defendants not domiciled in a Contracting State
[Member State] made it possible to bring another defendant, domiciled
in a Contracting State [Member State], before that same court in cases
other than those envisaged by the Convention, thereby depriving him
of the benefit of the protective rules laid down by it.
ECJ
27 September 1988 'Athanasios v Bankhaus Schröder c.s.' (Case
189/87, ECR 1988 p. 05565)
For Article 6, point 1, of the 1968 Brussels Convention
[Article 6, point 1, of the Brussels I Regulation] to apply, a connection
must exist between the various actions brought by the same plaintiff
against different defendants. That connection, whose nature must be
determined independently, must be of such a kind that it is expedient
to determine the actions together in order to avoid the risk of irreconcilable
judgments resulting from separate proceedings.
Third party in third-party proceedings [Article 6,
point (2)]
ECJ
26 May 2005 ‘GIE c.s. v Zurich’ (Case
C-77/04, ECR 2005 p. I-04509)
Article 6, point 2, of the 1968 Brussels Convention
[Article 6, point 2, of the Brussels I Regulation] is applicable to
third-party proceedings between insurers based on multiple insurance,
in so far as there is a sufficient connection between the original
proceedings and the third-party proceedings to support the conclusion
that the choice of forum, made on the basis of the provisions of the Brussels Convention [Brussels I Regulation] and not on the basis of a contractual choice of forum, does not amount to an abuse. It is for the
national court seised of the original claim to verify the existence
of such a connection, in the sense that it must satisfy itself that
the third-party proceedings do not seek to remove the defendant from
the jurisdiction of the court which would be competent in the case
(see paras 32, 36, operative part 2).
ECJ
15 May 1990 ‘Agentur Hagen v Zeehaghe’ (Case
C-365/88, ECR 1990 p. I-01845)
Where a defendant domiciled in a Contracting State
[Member State] is sued in a court of another Contracting State [Member
State] pursuant to Article 5, point 1, of the 1968 Brussels Convention
[Article 5, point 1, of the Brussels I Regulation], that court also
has jurisdiction by virtue of Article 6, point 2, of that Convention
[Article 6, point 2, of that Regulation] to entertain an action on
a warranty or guarantee brought against a person domiciled in a Contracting
State [Member State] other than that of the court seised of the original
proceedings. To enable the entire dispute to be heard by a single
court, Article 6, point 2 [Article 6, point 2, Regulation], simply
requires there to be a connecting factor between the main action and
the action on a warranty or guarantee, irrespective of the basis on
which the court has jurisdiction in the original proceedings.
Article 6, point 2 [Article 6, point 2, Regulation]
must be interpreted as meaning that it does not require the national
court to accede to the request for leave to bring an action on a warranty
or guarantee and that the national court may apply the procedural
rules of its national law in order to determine whether that action
is admissible, provided that the effectiveness of the 1968 Brussels
Convention [the Brussels I Regulation] in that regard is not impaired
and, in particular, that leave to bring the action on the warranty
or guarantee is not refused on the ground that the third party resides
or is domiciled in a Contracting State [Member Stae] other than that
of the court seised of the original proceedings.
Counterclaim arising from the same contract or facts
as the original claim [Article 6, point (3)]
ECJ
26 May 2005 ‘GIE c.s. v Zurich’ (Case
C-77/04, ECR 2005 p. I-04509)
Third-party proceedings between insurers based on
multiple insurance are not subject to the rules of special jurisdiction
in matters relating to insurance in Section 3 of Title II of the 1968
Brussels Convention [Section 3 of Title II of the Brussels I Regulation].
In affording the insured a wider range of jurisdiction than that available
to the insurer and in excluding any possibility of a clause conferring
jurisdiction for the benefit of the insurer, the provisions of that
section reflect an underlying concern to protect the insured, who
in most cases is faced with a predetermined contract, the clauses
of which are no longer negotiable, and is the weaker party economically.
No special protection is justified since the parties concerned are
professionals in the insurance sector, none of whom may be presumed
to be in a weaker position than the others (see paras 17, 20, 24,
operative part 1).
ECJ
13 July 1995 ‘Danværn v Schuhfabriken Otterbeck’ (Case
C-341/93, ECR 1995 p. I-02053)
Article 6, point 3, of the 1968 Brussels Convention
[Article 6, pont 3, of the Brussels I Regulation] is intended to establish
the conditions under which a court has jurisdiction to hear a claim
which would involve a separate judgment or decree. It therefore applies
only to claims by defendants which seek the pronouncement of such
a judgment or decree. It does not apply to the situation where a defendant
raises, as a pure defence, a claim which he allegedly has against
the plaintiff. The defences which may be raised and the conditions
under which they may be raised are governed by national law.
|